Client Account · Project Tracker
PT Procter & Gamble Home Products Indonesia · FMCG · Personal Care & Home
P&G Indonesia — 2026 Delivery Timeline
Proposed vs actual per project · Indonesia working calendar · excludes weekends & public / joint holidays.
8
Projects
4
On track
1
Late
3
Pending
Brand portfolio
CorporateCorporate2−1
PanteneHair Care1+1
RejoiceHair Care1+1
GilletteShave & Oral Care1
Head & ShouldersHair Care1
DownyFabric Care1
Oral-BShave & Oral Care1
Showing 8 / 8
| # | Project | Plan | Briefing Date | Design Process | Mockup Creation | Mockup Approval | Quotation Submitted | PO Date | Production Timeline | Delivery | SOS | Total E2E Working Days | Hit / Miss |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | Pantene — Miracle Hair Rescue POSM PGID-001•Pantene·Hair Care ClosedArina K. Briefing Design Mockup Quotation PO Production Delivery Closed 100% done | Plan | Briefing Date | Design Process | Mockup Creation | Mockup Approval | Quotation Submitted | PO Date | Production Timeline | Delivery | SOS | Total E2E Working Days | Hit / Miss |
| Proposed | → 4 days | → 2 days | → 1 day | → 7 days | → 13 days | 35 wd | +2 earlier | ||||||
| Actual | ReceivedCompleted | ReadyApproved | Mockup
Submission | 1st SubmissionFinal Approval | StartDone | → 4 days | 30 wd | ||||||
| 02 | Rejoice — Thick & Long Shampoo POSM PGID-002•Rejoice·Hair Care ClosedBagus W. Briefing Design Mockup Quotation PO Production Delivery Closed 100% done | Plan | Briefing Date | Design Process | Mockup Creation | Mockup Approval | Quotation Submitted | PO Date | Production Timeline | Delivery | SOS | Total E2E Working Days | Hit / Miss |
| Proposed | → 4 days | → 2 days | → 1 day | → 14 days | → 8 days | 37 wd | +2 earlier | ||||||
| Actual | ReceivedCompleted | ReadyApproved | Mockup
Submission | 1st SubmissionFinal Approval | StartDone | → 7 days | 35 wd | ||||||
| 03 | Gillette — Fusion5 Gift Set PGID-003•Gillette·Shave & Oral Care ClosedCitra D. Briefing Design Mockup Quotation PO Production Delivery Closed 100% done | Plan | Briefing Date | Design Process | Mockup Creation | Mockup Approval | Quotation Submitted | PO Date | Production Timeline | Delivery | SOS | Total E2E Working Days | Hit / Miss |
| Proposed | → 6 days | → 3 days | → 3 days | → 16 days | → 12 days | 48 wd | 0 exact | ||||||
| Actual | ReceivedCompleted | ReadyApproved | Mockup
Submission | 1st SubmissionFinal Approval | StartDone | → 12 days | 48 wd | ||||||
| 04 | Head & Shoulders — Road-show Booth PGID-004•Head & Shoulders·Hair Care DesignDewi P. Briefing Design Mockup Quotation PO Production Delivery Closed 38% done | Plan | Briefing Date | Design Process | Mockup Creation | Mockup Approval | Quotation Submitted | PO Date | Production Timeline | Delivery | SOS | Total E2E Working Days | Hit / Miss |
| Proposed | → 6 days | → 3 days | → 3 days | → 18 days | → 5 days | 42 wd | pending | ||||||
| Actual | ReceivedCompleted | ReadyApproved | Mockup
Submission | 1st SubmissionFinal Approval | StartDone | → | 15 wd | ||||||
| 05 | Downy — Perfume Collection Endcap PGID-005•Downy·Fabric Care ClosedEko S. Briefing Design Mockup Quotation PO Production Delivery Closed 100% done | Plan | Briefing Date | Design Process | Mockup Creation | Mockup Approval | Quotation Submitted | PO Date | Production Timeline | Delivery | SOS | Total E2E Working Days | Hit / Miss |
| Proposed | → 4 days | → 2 days | → 3 days | → 14 days | → 9 days | 39 wd | 0 exact | ||||||
| Actual | ReceivedCompleted | ReadyApproved | Mockup
Submission | 1st SubmissionFinal Approval | StartDone | → 9 days | 37 wd | ||||||
| 06 | Oral-B — Dentist Expo Activation PGID-006•Oral-B·Shave & Oral Care QuotationFira N. Briefing Design Mockup Quotation PO Production Delivery Closed 38% done | Plan | Briefing Date | Design Process | Mockup Creation | Mockup Approval | Quotation Submitted | PO Date | Production Timeline | Delivery | SOS | Total E2E Working Days | Hit / Miss |
| Proposed | → 5 days | → 2 days | → 3 days | → 13 days | → 12 days | 43 wd | pending | ||||||
| Actual | ReceivedCompleted | ReadyApproved | Mockup
Submission | 1st SubmissionFinal Approval | StartDone | → | 13 wd | ||||||
| 07 | Corporate — Internal Brand Activation PGID-007•Corporate·Corporate ClosedGilang R. Briefing Design Mockup Quotation PO Production Delivery Closed 100% done | Plan | Briefing Date | Design Process | Mockup Creation | Mockup Approval | Quotation Submitted | PO Date | Production Timeline | Delivery | SOS | Total E2E Working Days | Hit / Miss |
| Proposed | → 6 days | → 2 days | → 1 day | → 18 days | → 11 days | 46 wd | −3 late | ||||||
| Actual | ReceivedCompleted | ReadyApproved | Mockup
Submission | 1st SubmissionFinal Approval | StartDone | → 10 days | 48 wd | ||||||
| 08 | Corporate — HUT RI Annual Gala PGID-008•Corporate·Corporate BriefingHana L. Briefing Design Mockup Quotation PO Production Delivery Closed 0% done | Plan | Briefing Date | Design Process | Mockup Creation | Mockup Approval | Quotation Submitted | PO Date | Production Timeline | Delivery | SOS | Total E2E Working Days | Hit / Miss |
| Proposed | → 7 days | → 3 days | → 3 days | → 15 days | → 5 days | 42 wd | pending | ||||||
| Actual | ReceivedCompleted | ReadyApproved | Mockup
Submission | 1st SubmissionFinal Approval | StartDone | → | — wd |
Hit / Miss color key
−3
Late (minus)
Actual later than proposed
+5
Earlier
Delivered ahead of plan
0
Exact
On the day planned
Working days only — weekends and Indonesian public & joint holidays are excluded.